1. Name of activity:
Embankment Construction
2. Highway Activities
3. Description of Activity:
Construction of Embankment Layers with all lifts and
leads complete as per MORT&H technical Specifications clause 305 and as per
the direction of Employer/Consultant/Engineer.
Acceptance Criteria: Min.95% of MDD & as per Cl.
903.2.2
4. References:
a) Ref. to Technical Specification (MORT&H Spec. & Amendments)
a.1) Clauses: 305,903.2.2
a.2) Tables: 300-1, 300-2.
b) Ref. other related works prior to this activity:
b.1) OGL Approval, Borrow Area Approval, Level Recording.
c) Ref. to Drawing(s):
c.1) Nil
d) IS/IRC Specifications
d.1) Nil
5. Scope of Work:
This work shall consist of construction of Embankment with the
approved material from Roadway, drain excavation and borrow pits or any other sources approved by Employer/Consultant/Engineer.
MANPOWER REQUIREMENT:
1. Section In charge
2. Site In charge
3. Section Engineer
4. Site Supervisor
MACHINERY REQUIREMENT:
Excavator, Dumper, Motor Grader,
Water Tanker and Vibro roller.
Setting out will be done prior to work demarking the area of execution.
The embankment
material shall be spread in layers of uniform thickness not exceeding
250 mm compacted thickness over the entire width of embankment by mechanical
means, finished by a motor grader and compacted as per Clause' 305.3.6. Maintain
the same so as to achieve the specific slope and grade. Successive layers shall
not be placed until the layer under construction has been thoroughly compacted
to the specified requirements as in Table 300-2 and got approved by the
Engineer. Each compacted layer shall be finished parallel to the final
cross-section of the embankment. Moisture content of the material shall be
checked at the site of placement prior to commencement of compaction; if found
to be out of agreed limits, the same shall be made good. Where water is
required to be added in such constructions, water shall be sprinkled from a
water tanker fitted with sprinkler capable of applying water uniformly with a
controllable rate of flow to variable widths of surface but without any
flooding. The water shall be added uniformly and thoroughly mixed in soil by
blending, dicing or harrowing until uniform moisture content is obtained
throughout the depth of the layer.
If the material delivered to the roadbed is too wet,
it shall be dried, by aeration and exposure to the sun, till the moisture
content is acceptable for compaction. Should circumstances arise, where owing
to wet weather, the moisture content be reduced to the required amount by the
above 'procedure. Compaction work shall be suspended. Moisture content of each
layer of soil shall be checked in accordance with IS: 2720 (part 2), and unless
otherwise mentioned, shall be so adjusted, making due allowance for evaporation
losses, that at the time of compaction it is in the range of 1 per cent above
to 2 per cent below the optimum moisture content determined in accordance
with 1S:2720 (Part 8) as the case may
After adding the required amount of water, the soil shall be processed by means
of graders, harrows, rotary mixers or as otherwise approved by the Engineer
until the layer is uniformly wet. Clods or hard lumps of earth shall be broken
to have a maximum size of 75 mm when being placed in the embankment
Safety and
Environmental Activities:
a) Caution Boards will be placed at the beginning and end
of working site and also at risky locations.
b) Signal man will be placed at heavy traffic locations
at the time of Execution.
c) Reflective sign boards will be placed during night
near risky locations.
d) All necessary measures shall be taken to control the
disposal of all forms of waste generated by the construction operations and in
all associated activities.
e) All necessary measures and precautions shall be taken
to avoid any nuisance or disturbance arising from the execution of the work.
Any other
points the contractor likes to mention:
a) The manpower & machinery proposed is indicative
only. The requisite quantity of resources may vary based upon site condition.
b) Any modification in execution of activity shall be
done with prior information with consultant.
No comments:
Post a Comment